[April 2018] 2018 Exam PMP Dumps From Lead2pass Cover All New PMP New Questions 1720q

Posted in PMI, PMP Dumps, PMP Exam Questions, PMP New Questions, PMP PDF, and PMP VCE

2018 Lead2pass New Updated PMP Exam Questions:

https://www.lead2pass.com/pmp-exam.html

QUESTION 21
Because your project is slated to last five years, you believe rolling wave planning is appropriate. It provides information about the work to be done______________.

A.    Throughout all project phases
B.    For successful completion of the current project phase
C.    For successful completion of the current and subsequent project phases
D.    In the next project phase

[January 2018] Easily Pass PMP Exam With Lead2pass Updated PMI PMP Dumps 1720q

Posted in PMI, PMP Dumps, PMP Exam Questions, PMP New Questions, PMP PDF, and PMP VCE

Easily Pass PMI PMP Exam With Lead2pass Latest PMI PMP Brain Dumps:

https://www.lead2pass.com/pmp-exam.html

QUESTION 1
You work for a software development company that has followed the waterfall development model for more than 20 years. Lately, a number of customers have complained that your company is taking too long to complete its projects. You attended a class on agile development methods and believe that if the company used the agile approach, it could provide products to clients in a shorter time period. However, it would be a major culture change to switch from the waterfall methodology to the agile approach and to train staff members in this new approach. You mentioned this idea to the director of the PMO, and although she liked the idea, she would need approval from the company’s portfolio review board to move forward with it. She suggested that you document this idea in a______________.

A.    Business need
B.    Product scope description
C.    Project charter
D.    Business case